Fileman Lab Agile Project releases project plan
Rick Marshall | OSEHRA Blog | January 1, 2013
We are now halfway through phase 1 of the Fileman Lab Agile Project [FLAP], with three months done and three to go. During the next three months we will be doing the following:
- Beta test Fileman 22.2.
- Fix any remaining critical bugs in Fileman 22.2.
- Collect bug reports and enhancement requests for Fileman 22.3 and beyond.
- Finish documenting Fileman 22.2.
- Formally verify Fileman 22.2.
- OSEHRA-certify Fileman 22.2.
- Release Fileman 22.2 through OSEHRA.
- Help VA (and other adopters) install Fileman 22.2.
- Prepare for phase 2 of the Fileman Lab Agile Project...
- Login to post comments